Adjusting Resource Assignments
As you schedule your project, you assign some number of resources to
tasks, depending on how much help you need (and how many helpers you
can manage). After you complete a draft schedule, you often end up
fine-tuning some assignments—and that requires finesse, as discussed in
the box on The Fine Art of Assigning Resources.
For example, stakeholders may try to throw resources at a problem, only
to have learning curves and chaos delay the task even more. Additional
resources can increase costs, which may or may not be OK, as you learn
on Paying More for Faster Delivery.
Experienced project managers know that most schedule problems have several solutions. For example, if you find
underallocated resources working on critical path tasks, you can
increase their assignment units to shorten task durations. Or you can
look for a person with the right skills and more available time. If
you’re trying to cut costs, you can look at replacing expensive
resources with people with lower rates.
Increasing Units to Decrease Duration
Before you ask people to work extra hours, look for resources on
critical path tasks who have time available. You can assign them more
work to reduce critical task duration. Project doesn’t have a dedicated
view for this combination of conditions. However, you can filter a
task-oriented view to show the critical path and alter the Resource
Graph to show available time, as illustrated in Figure 9.
Selecting a task in the table area shows the first resource assigned
to that task in the Resource Graph in the bottom pane. To see other
resources assigned to the task, click the horizontal scroll bar under
the resource legend (on the left).
To see the Tracking Gantt in the top pane of a view, and the Resource Graph in the bottom pane, do the following:
-
Choose Task→View. Click the down arrow to the right of the view button, and then, on the drop-down menu, choose Tracking Gantt.
Project displays the Tracking Gantt view. You can use the Detail
Gantt or the Task Entry view if you’ve formatted it to show critical
tasks.
-
Choose View→Split View. Turn on the Details checkbox, and then choose Resource Graph in the Details drop-down list.
The Resource Graph appears in the bottom pane of the view.
-
Click the bottom pane to make it active.
You can tell the bottom pane is active when the narrow vertical bar
on the left side of the pane is dark, while the vertical bar in the top
view is a lighter shade.