IT tutorials
 
Office
 

Microsoft Project 2010 : Assigning Resources to Tasks - Assigning Cost Resources to Tasks

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
3/5/2013 11:44:13 AM

Assigning Cost Resources to Tasks

Cost resources do no work and have no effect on the scheduling of a task. Cost resources might include categories of expenses that you want to budget and track for accounting or financial reporting purposes. Broadly speaking, the costs that tasks can incur can include:

  • Work resource costs, such as a person’s standard pay rate times the amount of work they perform on the task.

  • Cost resource costs, which are a fixed dollar amount that you enter when assigning the cost resource to a task. The amount is not affected by changes in duration or any other schedule changes to the task, although you can edit the amount at any time. You can also see cumulative costs resulting from assigning the same cost resource to multiple tasks.

For the new book launch project plan, you’d like to enter planned travel costs for certain tasks. Since work has not yet started on this project at this time, these costs represent planned costs (indeed, you should consider all costs that Project has calculated so far in the schedule to be planned costs, such as those resulting from work resource assignments to tasks). Later, you can enter actual costs if you wish to compare them with the budget.

In this exercise, you assign a work resource and a cost resource to a task and check the plan’s overall duration and cost values.

  1. Click the name of task 17, Author reading and signing at book fair.

    This task requires air travel by the author, and you’ve allocated $800 in anticipation of this expense.

    Currently task 17 has no assigned resource and no cost. First, you’ll assign the author to the task.

  2. In the Resource Name column in the Assign Resources dialog box, click Toni Poe, and then click Assign.

    Assigning Cost Resources to Tasks

    Project assigns Toni Poe, a work resource, to the task. As you can see in the Cost field of the Assign Resources dialog box, this assignment has no cost. That’s because this work resource, Toni Poe, has no cost rate or per-use cost. So even though the assignment generated work, there’s no cost associated with it. Next, you’ll assign the cost resource.

  3. In the Assign Resources dialog box, select the Cost field for the Travel cost resource, type 800, and then click Assign.

    Project assigns the cost resource to the task.

  4. To see both assigned resources, scroll up the Resource list in the Assign Resources dialog box.

    Assigning Cost Resources to Tasks

    You can see the cost incurred by this assignment in the Cost column of the Assign Resources dialog box. The travel cost value will remain the same regardless of any changes made to the scheduling of the task, such as work resources being assigned or unassigned, or the task’s duration changing.

    Note the task has the same duration of one day and Toni Poe has the same units and work values as before. Assigning the cost resource affected only the cost incurred by this task.

    To conclude this exercise, you’ll revisit the project’s overall duration and cost values now that you’ve made some resource assignments.

  5. On the Project tab, in the Properties group, click Project Information, and then click Statistics.

    Assigning Cost Resources to Tasks
    Assigning Cost Resources to Tasks

    Note the shorter duration of 36 days (it had been 41 days) and the $19,740 cost. The shorter duration is the result of applying effort-driven scheduling to some tasks. The cost is the sum of work resource assignments plus the one cost resource assignment.

  6. Click Close.

Clean Up

Close the Simple Assignments file.

 
Others
 
- Microsoft Project 2010 : Assigning Resources to Tasks - Controlling Work When Adding or Removing Resource Assignments
- Microsoft Project 2010 : Assigning Resources to Tasks - Assigning Work Resources to Tasks
- Microsoft PowerPoint 2010 : Sharing a Presentation on the Web - Broadcasting a Presentation
- Microsoft PowerPoint 2010 : Sharing a Presentation on the Web - Saving as a PDF File, Creating a Video
- Microsoft PowerPoint 2010 : Saving a Presentation to the Web
- Microsoft Outlook 2010 : Modifying and Updating a Task
- Microsoft Outlook 2010 : Working with Recurring Tasks
- Microsoft Excel 2010 : Macros and UDFs - Recording a Macro
- Microsoft Excel 2010 : Macros and UDFs - Understanding How the Macro Recorder Works
- Microsoft Excel 2010 : Macros and UDFs - Enabling VBA Security
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us