IT tutorials
 
Office
 

Microsoft Project 2010 : Assigning Resources to Tasks - Assigning Work Resources to Tasks

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
3/5/2013 11:41:27 AM
Assigning a work resource to a task enables you to track the progress of the resource’s work on the task. If you enter resource pay rates, Project also calculates resource and task costs for you.

The capacity of a resource to work is measured in units (a level of effort measurement), and recorded in the Max. Units field. Unless you specify otherwise, Project assigns 100 percent of the units for the resource to the task—that is, Project assumes that all the resource’s work time can be allotted to the task. If the resource has less than 100 percent maximum units, Project assigns the resource’s Max. Units value.

In this exercise, you make some initial resource assignments to tasks.

Set Up

Start Project if it’s not already running.

  1. On the File tab, click Save As.

    Project displays the Save As dialog box.

  2. In the File name box, type Simple Assignments, and then click Save.

    Before making any resource assignments, you’ll check the project plan’s current duration and cost values for later comparison.

  3. On the Project tab, in the Properties group, click Project Information, and then click Statistics.

    Set Up
    Set Up

    Note the current duration of 41 days and zero cost. After you assign work and cost resources, you’ll check these values again.

  4. Click Close.

    Next you’ll make your first resource assignment.

  5. On the Resource tab, in the Assignments group, click Assign Resources.

    Set Up

    The Assign Resources dialog box appears, in which you see the resource names, plus additional resources.

    Set Up

    Except for assigned resources, which always appear at the top of the list, resources are sorted alphabetically in the Assign Resources dialog box.

    Important

    If you are using Project Professional rather than Project Standard, the Assign Resources dialog box and some other dialog boxes you see will contain additional options relating to Project Server.

  6. In the Task Name column, click the name of task 2, Assign launch team members.

  7. In the Resource Name column in the Assign Resources dialog box, click Carole Poland, and then click Assign.

    Important

    A cost value and check mark appears next to Carole’s name, indicating that you have assigned her to the task. Carole’s name also appears next to the task 2 Gantt bar. Because Carole has a standard cost rate recorded, Project calculates the cost of the assignment (Carole’s standard pay rate times her scheduled amount of work on the task) and displays that value, $420, in the Cost field of the Assign Resources dialog box.

  8. In the Task Name column, click the name of task 3, Complete author questionnaire.

  9. In the Resource Name column in the Assign Resources dialog box, click Toni Poe, and then click Assign.

    Important

    Tip

    To remove or unassign a resource from a selected task, in the Assign Resources dialog box, click the resource name, and then click Remove.

    Next, you’ll take a closer look at the details of task 3. You’ll use a handy view called the Task Form.

  10. On the View tab, in the Split View group, click Details.

    Project splits the window into two panes. In the upper pane is the Gantt Chart view, and below it is the Task Form.

    Tip

    You may recognize that the Task Form is similar to the Resource Form but shows different details. In this type of split view, the details about the selected item in the upper view (a task, in this case) appear in the lower view, similar to the Resource Form. The Task Form displays one of several details. Next you’ll change the displayed details.

  11. Click anywhere in the Task Form and then, on the Format tab, in the Details group, click Work.

    Tip

    The Work details appear.

    Tip

    Now, in the Task Form, you can see the essential scheduling values for this task: 1 week duration, 40 hours of work, and 100% assignment units. Because the Task Form is a handy way to see a task’s duration, units, and work values, you’ll leave it displayed for now.

  12. Using the Assign Resources dialog box, assign the following resources to tasks. As you do so, note the Duration, Units, and Work values in the Task Form.

    For this task

    Assign this resource

    4, Schedule author interviews

    Jun Cao

    5, Design and order marketing material

    Toby Nixon

    When you are finished, your screen should look similar to the following illustration.

    Tip

    Next, you will assign two resources to a single task.

  13. In the Task Name column, click the name of task 8, Kickoff book launch meeting.

  14. In the Assign Resources dialog box, select the names of Sharon Salavaria and Toby Nixon, and then click Assign.

    Tip

    To select nonadjacent resource names, select the first name, hold down the Ctrl key, and then select additional names.

    Sharon and Toby are assigned to the task. You can also see their names next to task 8’s Gantt bar.

    Tip

    Sharon has a 50% Max. Units value to account for her half-time schedule. As a result, Project assigned her at 50% units.

    To conclude this exercise, you’ll use a different means of assigning resources.

  15. In the Gantt Chart view, drag the vertical divider bar to the right until the Resource Names column is visible.

  16. Click in the Resource Names column for task 9, Plan author’s travel itinerary, and then click the arrow that appears.

    The resource names appear.

    Tip
  17. In the list of resource names, click the check boxes for Jane Dow and Zac Woodall, and then press the Enter key.

    Jane and Zac are assigned to task 9.

    Tip
  18. Click in the Resource Names column for task 10, Channel Sales prep, and then click the arrow that appears. In the list of resource names that appears, check Zac Woodall and then press the Enter key.

    Zac is assigned to task 10.

Tip

In this exercise, you assigned resources using the Assign Resources dialog box and the Resource Names column in the Gantt Chart view. In addition, you can assign resources in the Task Form and on the Resources tab of the Task Information dialog box, among other places. As you use Project, you’ll likely develop your own preference for the way you assign resources.

The Scheduling Formula: Duration, Units, and Work

After you create a task, but before you assign a resource to it, the task has duration but no work associated with it. Why no work? Work represents the amount of effort a resource or resources will spend to complete a task. For example, if you have one person working full time, the amount of time measured as work is the same as the amount of time measured as duration. In general, the amount of work will match the duration unless you assign more than one resource to a task or the one resource you assign is not working full time.

Project calculates work using what is sometimes called the scheduling formula:

Duration × Units = Work

Let’s look at a specific example and find these values in the Task Form. The duration of task 3 is one week, or five working days.

40 hours (same as one week) task duration × 100% assignment units = 40 hours of work

In other words, with Toni assigned to task 3 at 100% units, the task should require 40 hours of work.

Here’s a more complex example. You assigned two resources, Jane Dow and Zac Woodall, to task 9, each at 100% assignment units. The scheduling formula for task 9 looks like this:

24 hours (same as three days) task duration × 200% assignment units = 48 hours of work

The 48 hours of work is the sum of Jane’s 24 hours of work plus Zac’s 24 hours of work. In other words, as currently scheduled, both resources will work full time on the task in parallel for its three-day duration.

 
Others
 
- Microsoft PowerPoint 2010 : Sharing a Presentation on the Web - Broadcasting a Presentation
- Microsoft PowerPoint 2010 : Sharing a Presentation on the Web - Saving as a PDF File, Creating a Video
- Microsoft PowerPoint 2010 : Saving a Presentation to the Web
- Microsoft Outlook 2010 : Modifying and Updating a Task
- Microsoft Outlook 2010 : Working with Recurring Tasks
- Microsoft Excel 2010 : Macros and UDFs - Recording a Macro
- Microsoft Excel 2010 : Macros and UDFs - Understanding How the Macro Recorder Works
- Microsoft Excel 2010 : Macros and UDFs - Enabling VBA Security
- Microsoft Word 2010 : Working with Styles (part 3) - Deleting Styles, Revealing Formatting
- Microsoft Word 2010 : Working with Styles (part 2) - Creating Customized Styles, Managing Styles
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us