IT tutorials
 
Office
 

Microsoft Project 2010 : Work Breakdown Structure (part 1) - Work Breakdown Structure Concepts

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
4/25/2014 4:40:58 AM
After you have clarity on the goal, boundaries, and constraints for your project, it is time to begin the process of identifying all of the work by decomposing the goal into manageable pieces. Of all the projects that fail, most are due to a failure to identify all of the changes to scope or to manage these changes. The PMBOK Guide recommends the use of the Work Breakdown Structure (WBS) as the best practice for identifying and managing packages of work in a project schedule. The identification and management of these packages of work are critical to understanding and maintaining project scope.

This section covers key principles of building and using a WBS with a focus on creation of the WBS for accurate and effective management of Microsoft Project schedules. It is important that your schedule is an accurate reflection of the work required to reach a successful conclusion of your project. Using a WBS will help you reach that goal by ensuring you cover 100% of the scope of your project without adding activities that are not related.

Work Breakdown Structure (WBS) Concepts

You can create a WBS using Project, but it is often more useful to create the first iteration on a whiteboard because it will change multiple times before you are ready to finalize it. The iterative process typically begins with a top-down decomposition of deliverables through successive levels of detail until you reach a level where the work can be planned and controlled. This level is called a work package. All levels of decomposition from Level 1 (the project) through the lowest level (work package) are noun-based and focus on the deliverable, not how the deliverable is achieved. Many levels may be required, depending on the complexity of the project, and not all branches of the WBS will require the same number of sublevels of breakdown. The lowest-level WBS element (the work package) will eventually contain the set of activities or tasks that need to be performed to accomplish the achievement identified by the work package. A work package should be able to be assigned to one work group or an individual for performance. If that cannot be done, it may not be broken out as far as it should be.

The example in Figure 1 shows the levels of decomposition that are used in a WBS to break a project into the appropriate work packages.

Figure 1. Work is decomposed to the lowest level needed for effective management and tracking (work package).

Decomposition of work into appropriate work packages and the associated activities for those packages can be reflected in Microsoft Project as well. The lowest level of the WBS—the work package—will be represented by a summary task. You should keep together all activities within that work package and link them with a starting and an ending milestone.

Figure 2 shows an example of a task activity list in Project that is derived from the WBS example in Figure 1.

Figure 2. Work packages within Project should have a starting and an ending milestone.

There are a few rules regarding building a WBS that you should keep in mind when developing a schedule in Project:

  • Number of levels— The number of levels in a WBS will vary with the complexity of the project. Some elements may have more levels of detail than others. Elements are described with nouns and adjectives.

  • Level 2 elements— This level includes project management and at least one other element, depending on the type of deliverables to be produced by the project: product, service, or result. There may also be additional elements at Level 2 and below that support neighboring elements (cross-cutting elements) or represent the next step in a process. See Figure 3 for an example.

    Figure 3. Level 2 elements include Management and at least one other element based on the type of deliverables that the project will produce.
  • Level 3 and below (work package elements)— Decomposition continues as needed until the work package, the lowest element of a WBS, is reached. It must be at a level of decomposition sufficient to be controlled and performed by one individual or one organizational entity. A work package is broken into activities and tasks that are described with a verb (see Figure 3).

  • WBS dictionary— Each element of a WBS may be described in more detail in a WBS dictionary. Additional information about the element, including budget, cost, and earned value data may also be included there.

  • 100% rule— Each lower level of decomposition must represent all of the work of the higher-level element; conversely, all higher-level scope must be reflected in one of the lower-level elements. This is called the 100% rule, which ensures that all of the scope has been captured and that nothing extraneous is included.

As you can see from these examples, the WBS can be created in Microsoft Project or as a whiteboard exercise prior to opening a schedule. The Practice Standard for Work Breakdown Structures, Second Edition (PMI, 2006) recommends that the team be involved in the creation of the WBS. The focus for this process should be on the outputs to be produced so that the team uses nouns to describe what will be produced and can identify all of the cross-cutting elements that are required.

 
Others
 
- Microsoft Project 2010 : Getting Started After the Business Initiative Is Approved - Organizing for Success
- Microsoft Visio 2010 : Cleaning Up Documents - Setting Document Properties,Removing Personal Information , Reducing File Size
- Microsoft Visio 2010 : Working with SharePoint - Working with Files in Document Libraries
- Microsoft Visio 2010 : Exporting Visio Graphics to Other Formats
- Microsoft Visio 2010 : Using Visio Graphics with Other Applications
- Microsoft Visio 2010 : Saving Visio Files in XML Format, Saving Files in Older Visio Formats
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Setting Up a Slide Show
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Recording a Narration
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Adding Slide Timings
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Using the Animation Painter
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us