IT tutorials
 
Office
 

Microsoft Project 2010 : Entering Tracking Information at the Task Level (part 1)

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Malwarebytes Premium 4.1.0.56 – Licence Key / Serial Keys
3/29/2015 9:15:47 PM

Covers of this section how to employ to detect fields on the level of task to update the statute of task. It is how you would write progress manually, if you choose to employ this method.

This section looks at the following task-tracking fields:

  • Actual Start

  • Actual Finish

  • % Complete

  • Actual Duration

  • Remaining Duration

  • Actual Work

  • % Work Complete

  • Remaining Work

  • Time-Phased Work

You can view and edit most of these fields on the task by using the Gantt Chart view with the Tracking table columns showing (see Figure 1). To display the Tracking table in a task view, select the View tab, Tables, Tracking. To display the Work table in a task view, select the View tab, Tables, Work. You can edit the % Work Complete and Remaining Work fields, and you can enter time-phased work in the time-phased grid on the Task Usage view.

Figure 1. The task Tracking table gives you access to many of the fields needed for tracking progress at the task level.

Note

Keep in mind that Microsoft Project has different calculations for the “work” fields and the “%Complete” fields. By default, the %Work Complete for resource assignments and %Complete task fields are coupled such that an edit to either field updates the other field. You can decouple these two fields by selecting the File tab, Options, Schedule, and then clearing the Updating tasks status updates resource status check box. This means that it is possible to complete 100% of the work on a task and yet the % Complete for the duration field is not at 100%, but you then must manage each field individually for every task in the schedule.

 
Others
 
- Microsoft Project 2010 : Tracking Your Project’s Performance and Costs - Understanding the Fields Used in Updating the Project Schedule
- Microsoft Project 2010 : Tracking Your Project Progress - Working with Project Baselines (part 2) - Using Usage Views to Show Time-Phased Details
- Microsoft Project 2010 : Tracking Your Project Progress - Working with Project Baselines (part 1) - Viewing Baselines
- Microsoft Project 2010 : Performing a Schedule Reality Check - Baselining the Schedule
- Microsoft Visio 2010 : Adding Sophistication to Your Drawings - Working with background pages and borders
- Microsoft Visio 2013 : Adding Sophistication to Your Drawings - Managing pages and page setup
- Microsoft Excel 2013 : Checking Compatibility - Check Workbook Compatibility
- Microsoft Excel 2013 : Working with Accounts - Work with Online Accounts, Add Online Services
- Microsoft Excel 2013 : Saving a Workbook to Online Services - Save a Workbook to Online Storage
- Microsoft Excel 2013 : Saving a Workbook with Different Formats - Save a Workbook with Another Format
 
 
Top 10
 
 
Facebook
 
Technology FAQ
- Microsoft ebs security server configuration
- IIs7 on Windows server 2003
- How to Configure Failover Clusters With Win 2008 Server R2?
- Windows 2008 Network Load Balancing
- Windows Server 2008 - Group Policy Management - Remove Computer Management
- Remove shortcuts possibility in a web page or to put in favorite
- HTA Dynamic Drop Down List
- IIS host header and DNS
- VMware or MS Virtual Server?
- Adobe Acrobat 9 inserting tab pages
programming4us programming4us