IT tutorials
 
Office
 

Taking Microsoft Project 2010 for a Test Drive (part 3) - Listing project tasks

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
3/21/2014 1:13:11 AM

3. Creating a Project Schedule

Building a project schedule might seem as intimidating and interminable as constructing the Great Wall of China. But if you build your schedule stone by stone (or task by task), you’ll be done before you know it.

Tip

If you’re already a Project maven, you may have a favorite approach to building a schedule. In that case, consider following this test drive anyway—you may just learn some new Project tips and tricks.

For just about any kind of project, you can start constructing a schedule by asking yourself the following questions:

  • What work must be done to achieve the project’s objectives?

  • What tangible results must your project produce—and when?

  • How does each task depend upon the completion of other tasks?

  • Who’s going to do the work?

  • How long do they have to get it done?

3.1 What Work Must Be Done?

The foundation for any schedule is the work that will achieve the project’s objectives and deliver the desired results. Before you can do anything else, you need a list of the tasks to perform, from beginning the project to sweeping up the confetti at the end. This section describes how to build a list of individual tasks.

Listing project tasks

In this test drive, you’ll create the steps for part of the project schedule—preparing the food and drinks for the party. For extra practice, you can try filling out the rest of the schedule on your own.

  1. Start Project by choosing Start→All Programs→Microsoft Office→Microsoft Project 2010.

    Project opens a blank project, called something like Project1.

  2. To change your project’s start date, choose Project→Properties→Project Information.

    Remember, the shorthand in the instructions means you select the Project tab, go to the Properties section on that tab, and then click the Project Information button.

  3. In the Start Date box, select the starting date, and then click OK to close the dialog box.

    Chances are your project doesn’t start the same day you build your project schedule, so change the project’s start date to when you expect work to begin. Setting an accurate start date is important, since Project schedules new tasks to start as soon as possible—initially, the project start date.

    The Project Information dialog box, shown in Figure 3 also provides opportunities for specifying your project calendar, working time, and so on. For this test project, as for many other projects, the settings are fine as is. 

    As you can see, you don’t step through the ribbon tabs in sequence. When Project launches, it opens to the Task tab. If you’re ready to start a new project, you select the Project tab so you can specify the project start date before you create any tasks. However, if you want to open an existing project, choose the File tab.

    Figure 3. As you can see, you don’t step through the ribbon tabs in sequence. When Project launches, it opens to the Task tab. If you’re ready to start a new project, you select the Project tab so you can specify the project start date before you create any tasks. However, if you want to open an existing project, choose the File tab.

  4. Add your project’s first task: In the first row of the Task Name column, type Buy the food and then press Enter.

    For the moment, the task name is the only cell you must fill in. Because Project initially creates new tasks as manually scheduled, it leaves the duration for your first task blank. The icon in the Task Mode cell (a pushpin with a question mark) indicates that more information is needed. (You’ll fill in that information later.)

    Tip

    If you want Project to calculate your schedule for you, create tasks as Auto Scheduled. In the status bar at the bottom of the window, click New Tasks: Manually Scheduled, and then choose Auto Scheduled.

  5. Repeat step 4 to add the following tasks:

    • Make gourmet pizza fixings

    • Make pizza crusts

    • Assemble pizzas

    Figure 4 shows what the task list looks like when you’re done.

    Project leaves the duration blank because the tasks are created in manually scheduled mode. The pushpin with a question mark icon in the Task Mode cell tells you that information is missing. When you’re ready to commit to how long a task should take, simply type the duration in the Duration cell (as described on page 74).

    Figure 4. Project leaves the duration blank because the tasks are created in manually scheduled mode. The pushpin with a question mark icon in the Task Mode cell tells you that information is missing. When you’re ready to commit to how long a task should take, simply type the duration in the Duration cell.


    As your task list grows, so does the urge to group tasks. People have a hard time focusing on more than half a dozen things at a time, so gathering related tasks into groups makes the project schedule easier to grasp.

  6. Drag over the task rows to select all the tasks. Then choose Task→Insert→Insert Summary Task.

    Project inserts a new summary task above the selected tasks, named <New Summary Task>. The program indents the selected tasks to make them subtasks, as shown in Figure 5. You can see that the summary task is set to Auto Scheduled, which means Project calculates the values for the task. For example, the program sets the Duration to “1 day?” The question mark indicates that the duration is an estimate. It also sets the start date to the project start date.

  7. Type the name for the summary task, Prepare food and drinks, and press Enter.

    When Project inserts the new summary task, it selects the Task Name cell, so you can immediately type the name of the summary task.

  8. To create a summary task and subtasks at the same time, select a blank row in the task list and then choose Task→Insert→Summary.

    Project inserts a new summary task and one subtask, named <New Summary Task> and <New Task>.

    Summary tasks help group your work into logical chunks and make the big-picture view emerge from the details. What’s more, Project calculates the dates, duration, and other values for summary tasks from the totals of their subordinate tasks (although you can’t see that helpful feature this early in the process).

    Figure 5. Summary tasks help group your work into logical chunks and make the big-picture view emerge from the details. What’s more, Project calculates the dates, duration, and other values for summary tasks from the totals of their subordinate tasks (although you can’t see that helpful feature this early in the process).

  9. Type Prepare drinks in the new summary Task Name cell and press Enter. In the Task Name cell that contains <New Task>, type Buy drink fixings and press Enter.

    Project selects the next cell in the Task Name column. As you’ll see in the next step, the next tasks you add are subtasks to the summary task you just created.

  10. Repeat step 4 to add the following tasks:

    • Make ice

    • Assemble bar

Tip

To move tasks inward or outward at any time, select the tasks and then choose Task→Schedule→ Indent Task or Task→Schedule→Outdent Task. Indent Task is a green arrow pointing to the right. The green arrow for Outdent Task points to the left. (Outdent is Microsoftese for the opposite of indent. That is, outdenting moves a task out to the next higher level in the outline.) You can also move selected tasks inward or outward by positioning the pointer at the magic spot in a Task Name cell (over the text of the task name) where the mouse pointer turns into a double arrow. When you see the double arrow, drag the tasks to the left or right.

If you wish, experiment with adding additional tasks and summary tasks to your schedule.

 
Others
 
- Taking Microsoft Project 2010 for a Test Drive (part 2) - The Project Window
- Taking Microsoft Project 2010 for a Test Drive (part 1) - Navigating the Project Ribbon
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Using Specialized Animations
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Adding and Removing Animation
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Creating Slide Transitions
- Microsoft Visio 2010 : Laying Out Shapes (part 3) - Fine-tuning Layout
- Microsoft Visio 2010 : Laying Out Shapes (part 2) - Using Visio’s Layout Features - Experimenting with Layout
- Microsoft Visio 2010 : Laying Out Shapes (part 1) - Using Visio’s Layout Features
- Developing, Integrating, and Building Applications in Sharepoint 2013 (part 3) - User Interface Integration - Ribbon and Action Menus
- Microsoft Visio 2010 : Adding Structure to Your Diagrams - Annotating Shapes with Callouts
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us