What Results Must Your Project Produce—and When?
Waiting until the end to see whether a project meets its deadline
isn’t just stressful; it also doesn’t give you enough time to go back
and fix what went wrong. What’s more, managers, clients, or other
stakeholders expect regular status updates, so you need up-to-date
information to keep them happy. Setting up regular checkpoints,
appropriately called milestones,
gives you a chance to gauge your progress frequently. The earlier you
discover that the project is falling behind, the more easily you can
take corrective action before it’s too late—or too costly.
Milestones are perfect for identifying deliverables—the
tangible products or results required to complete a project—and when
they’re due. Every project has a major deliverable at the end: a
building ready to occupy, a book ready to read, or a design ready to
construct. But most projects include additional deliverables along the
way, like an approved blueprint or proof copy.
Adding milestones to a project schedule
A milestone typically appears at the end of the tasks that produce
the deliverable or achieve a key point in progress. Completing a
milestone is like crossing off an item on your To Do list. Project
makes it easy to add milestones to your schedule:
-
Click anywhere in the blank row
below the last task (“Assemble bar” in the current example) and then
choose Task→Insert→Milestone.
The Task Name cell is set to <New Milestone> and the Duration is 0 days.
Project switches the Gantt Chart task bar symbol to a diamond. (Don’t
worry about the date on the milestone just yet.) If you select a row
containing a task, Project would automatically insert a new row above
the selected row.
Tip
Because milestones have zero duration, you can add as many as you want without increasing the duration of the project.
-
In the Task Name cell, type Food and drinks ready.
One way to differentiate milestones from work tasks is to name the
milestone based on what was accomplished: “Documentation printed” or
“Design complete,” for example.
-
To move the milestone to the same
level as its summary task, make sure the milestone task is selected,
and choose Task→Schedule→Outdent Task (the green arrow pointing to the
left). (Keyboard mavens can press Alt+Shift+left arrow.)
Project places the milestone at the same level in the outline as the summary task, as shown in Figure 6.
There are actually two schools of thought regarding where milestones
sit in an outline. One is to place milestones at the same level as the
summary tasks that produce them (as in this example), so you can
collapse an outline to hide subordinate tasks, but still see summary
tasks and their
corresponding deliverables or milestones. Other folks prefer to keep
milestones as subtasks, so that the higher-level views show only
summary tasks. Try it both ways to see which works for you.
Now’s a good time to practice by adding milestones for other checkpoints in your schedule.