IT tutorials
 
Office
 

Taking Microsoft Project 2010 for a Test Drive (part 7) - How Long Will All These Tasks Take?

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
3/21/2014 1:17:37 AM

How Long Will All These Tasks Take?

The next step can be the most difficult part of scheduling. You need to look into your crystal ball and give your best guess—er, informed estimate—of how long each project step should take. You can find entire books on this subject alone.

Here are the steps for defining the duration of tasks:

  1. Click the Duration cell for the first pizza work task (“Buy the food”).

    You can enter durations for summary tasks only if you’ve set their task mode to Manually Scheduled . For auto-scheduled summary tasks, Project calculates the duration for you from the duration of the subtasks. Milestones, by definition, have zero duration.

  2. Enter the length of time (duration) you or your buddies think it will take to do that step (Figure 10).

    You can enter durations in minutes (m), hours (h), days (d), weeks (w), or months (mo). Type the number followed by the abbreviation for the unit you want to use. For example, type 3d for 3 days or 6h for 6 hours.

    When you type durations like 3d, 2w, or 8h, Project replaces the abbreviated units with more complete text. For example, when you type d, Project substitutes days. When you click a Duration cell, arrows appear, which you can click to increase or decrease duration by one unit.

    Figure 10. When you type durations like 3d, 2w, or 8h, Project replaces the abbreviated units with more complete text. For example, when you type d, Project substitutes days. When you click a Duration cell, arrows appear, which you can click to increase or decrease duration by one unit.

    Note

    If you don’t type a unit, then Project uses the unit specified in the “Duration entered in” Project option. Choose File→Options, select the Schedule tab, and then choose the units in the “Duration is entered in” drop-down list.

  3. Repeat step 2 for each task in the project.

    When you’re done, the schedule shows how long it should take to prepare for your party, as Figure 11 illustrates.

For most projects, you have to tweak your schedule to meet project objectives, such as finish date, budget, or scope. 

A complete schedule has many tasks with resources assigned to them, and links between the tasks. There’s no guarantee that your first pass at a schedule will meet your objectives, but you have to reach this point to find out. (To compare your schedule to this example, you can download a completed version, as described in the tip on page 65.)

Figure 11. A complete schedule has many tasks with resources assigned to them, and links between the tasks. There’s no guarantee that your first pass at a schedule will meet your objectives, but you have to reach this point to find out. (To compare your schedule to this example, you can download a completed version, as described in the tip on page 65.)

Saving Your Project

Now, save your hard work so you can come back to it later. You must save Project files, just like any document or spreadsheet.

  1. Choose File→Save.

    The Save As dialog box appears. If you’ve saved the project file before, then the Save dialog box appears.

  2. In the “File name” field, type a name, and then click Save.

    Project saves the file in the location you specified.

As you work on your project, remember to save early and save often. Pressing Ctrl+S to save a Project file is so fast that you can make it a habit in no time. 

Congratulations! You’ve created your first project.

 
Others
 
- Taking Microsoft Project 2010 for a Test Drive (part 6) - List the people on your project,Assign resources to tasks
- Taking Microsoft Project 2010 for a Test Drive (part 5) - Creating task dependencies
- Taking Microsoft Project 2010 for a Test Drive (part 4) - Adding milestones to a project schedule
- Taking Microsoft Project 2010 for a Test Drive (part 3) - Listing project tasks
- Taking Microsoft Project 2010 for a Test Drive (part 2) - The Project Window
- Taking Microsoft Project 2010 for a Test Drive (part 1) - Navigating the Project Ribbon
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Using Specialized Animations
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Adding and Removing Animation
- Microsoft PowerPoint 2010 : Preparing a Slide Show - Creating Slide Transitions
- Microsoft Visio 2010 : Laying Out Shapes (part 3) - Fine-tuning Layout
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us