IT tutorials
 
Office
 

Microsoft Project 2010 : Setting Up Task Dependencies

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
10/13/2011 11:35:21 AM
Some tasks in your project may have certain relationships with other tasks in your project. For example, you may have a task that can’t begin until another task has ended. These relationships are called dependencies. Project offers four different types of dependencies for your project’s tasks:
  • Finish-to-Start (FS)— A finish-to-start dependency is one in which a second task cannot begin until the first task has ended.

  • Start-to-Start (SS)— A start-to-start dependency is one in which a second task cannot begin until the first task has begun.

  • Finish-to-Finish (FF)— A finish-to-finish dependency is one in which a second task cannot finish until the first task has finished.

  • Start-to-Finish (SF)— A start-to-finish dependency is one in which a second task cannot finish until the first task has begun.

Figure 1 shows these four types of dependencies.

Figure 1. Project provides four types of dependencies.


Let’s walk through an example that uses all four of these types of dependencies. In this example, you are planning to remodel the kitchen and dining area in a home. You use Project to track each of the tasks involved in this process.

Here are the tasks you want to track for the remodel:

  • Rewire kitchen— This involves moving outlets, wiring through cabinets for a built-in microwave, and adding an outlet on a kitchen island.

  • Install new cabinets— This involves installing new wall cabinets, and cabinets to support a new countertop.

  • Paint— This involves painting both the kitchen and dining areas.

  • Install counters— This involves placing a new countertop on top of the new cabinetry.

  • Install new floors— This involves placing new flooring in both the kitchen and dining areas.

  • Install new appliances— This involves installing several new kitchen appliances.

Each task has some sort of dependency on another task. The “Rewire kitchen” task can’t be finished until the “Install new cabinets” task has started, because some of the wiring needs to be done through the new cabinetry (wiring for a built-in microwave, and an outlet on the island). This is a start-to-finish dependency in Project.

The “Paint” task has a start-to-start dependency on the “Rewire kitchen” task. That is, the painting can’t start until the electrician has started the process of rewiring. The electrician needs to have moved openings for outlets and light fixtures, as necessary, before the painters can come in and begin painting the kitchen and dining areas. The electrician doesn’t need to be done with all of his work for the remodel before the painters can start, just the portion of work that impacts the painters.

The “Install counters” task can’t start until the “Paint” task has finished. By setting up this finish-to-start dependency, you avoid getting drips of paint all over the shiny new countertops. This type of dependency is most commonly used in project plans.

The “Install new floors” task can’t finish until the “Paint” task has finished. The painters begin by painting the ceiling in both the kitchen and dining areas, then move on to painting the kitchen. After the kitchen is painted, the flooring installers begin their work in the kitchen, while the painters finish painting the dining room. The flooring team can’t finish its work until the painters have finished painting the dining room. At that time, the flooring team can finish its work by flooring the dining room. In Project, this is represented as a finish-to-finish task.

Finally, the “Install new appliances” task can’t start until the “Install new floors” task has finished. This is another finish-to-start dependency.

Project represents these task dependencies on the Gantt chart using arrows between the tasks. Figure 2 shows how our example might look if we entered it into Project and set up the dependencies.

Figure 2. Example of dependencies within a project


Adding Dependencies Between Tasks

In Project, dependencies between tasks are recorded in the row for the second task in the dependency. For example, if you are creating a dependency in which Task B can’t start until Task A has finished (a finish-to-start dependency), you would record the dependency in the row for Task B. When you record the dependency, you indicate the task’s predecessor.

To quickly set start-to-finish dependencies between tasks in your project, select the rows for the tasks you want to link, and then, on the Task tab, in the ScheduleLink Tasks. group, click

If you want to set up other types of dependencies, create gaps between tasks, or overlap tasks, you can set up dependencies using the Predecessors column.

To set up a dependency between two tasks using the Predecessors column, follow these steps:

1.
In the Gantt Chart view, be sure the Predecessors column is displayed.



If the Predecessors column is not displayed, scroll all the way to the right of the table portion of the Gantt Chart view and then click Add New Column. Click Predecessors in the list that appears, to add the column to the view. You can click and drag the column header to move the column to another location in the table portion of the view.


2.
In the row for the second task in the dependency you’re creating, type the ID number (located in the row header) for the first task in the dependency in the Predecessors column. Also, indicate the dependency type.

For example, if you are creating a dependency between Task A (ID number 1) and Task B (ID number 2), you would type the following for each dependency type:

  • Finish-to-start— To indicate that Task B can’t start until Task A finishes, type 1 in the Predecessors column for Task B, as shown in Figure 3. Project assumes a finish-to-start dependency, by default, so you don’t need to include a dependency type abbreviation.

    Figure 3. In this example, Task B has a finish-to-start dependency on Task A.

  • Start-to-start— To indicate that Task B can start only after Task A has started, type 1SS in the Predecessors column for Task B.

  • Finish-to-finish— To indicate that Task B can finish only after Task A has finished, type 1FF in the Predecessors column for Task B.

  • Start-to-finish— To indicate that Task B can finish only after Task A has started, type 1SF in the Predecessors column for Task B.

3.
If one of your tasks needs to overlap another (known as “lead time”), or needs to fall behind another (known as “lag time”) by a certain amount, type this in the Predecessors column, as well:

  • Overlap two tasks— To overlap two tasks, type a negative duration, or percentage, after the task ID number and dependency type in the Predecessors column, as shown in Figure 4. For example, if you want Task B to start one day before Task A is scheduled to start, type 1SS-1d in the Predecessors column for Task B.
    Figure 4. Insert lead time in the Predecessors column.

  • Insert a delay between two tasks— If the second task needs a delay after the start or finish of the first task, type a positive duration, or percentage, after the task ID number and dependency type in the Predecessors column, as shown in Figure 5. For example, if you want Task B to start when Task A is 50% through its scheduled duration, type 1SS+50% in the Predecessors column for Task B.

    Figure 5. Insert lag time in the Predecessors column.

 
Others
 
- Microsoft Project 2010 : Understanding Task Types & Adding Tasks to Your Project
- Microsoft Access 2010 : Learning the Basics of Creating and Running a Macro (part 2) - Submacros, Program Flow
- Microsoft Access 2010 : Learning the Basics of Creating and Running a Macro (part 1) - Working with Macro Actions & Working with Action Arguments
- Microsoft Access 2010 : Deleting Records
- Microsoft Visio 2010 : Sharing Diagrams by Using the Visio Viewer
- Microsoft Visio 2010 : Creating Visio Templates
- Microsoft Word 2010 : Creating an XML Document
- Microsoft Word 2010 : Customizing Word - Linking and Embedding Files
- Microsoft PowerPoint 2010 : Saving a Presentation as a Slide Show & Saving a Presentation as a Video
- Microsoft PowerPoint 2010 : Delivering a Show on Multiple Monitors
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us