IT tutorials
 
Office
 

Microsoft Project 2010 : Setting Up Custom WBS Codes

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
12/21/2012 6:46:35 PM

The WBS codes built into Project are simple outline codes with a number for each level in the outline hierarchy. For instance, a WBS code of 2.1.3 might represent the second phase of the project, the first summary task in that phase, and the third work package for that summary task. If your organization uses custom codes, you can build a tailored numbering system—called a code mask—to specify each level of your WBS code. If you use abbreviations for phases, numbers for summary tasks, and letters for work packages, say, a customized WBS for the design phase of a project might look like this: Dsn 1.a.

To define a custom WBS code, follow these steps:

  1. On the Project tab, click WBS, and then choose Define Code.

    The WBS Code Definition dialog box appears. Although any existing WBS codes show numbers for each level with a period as a separator, the boxes in the WBS Code Definition dialog box are empty until you specify a custom scheme for your WBS codes.


    Note:

    If you assemble several projects into a single master project , you can make WBS codes unique for each project, even if they use the same code mask. If you work with multiple projects, set up the code mask for a new project before you get too deep into defining the project's tasks. That way you don't have to renumber all your tasks later. In the Project Code Prefix box, type a prefix for the current project, like "PRJ01." Project then inserts this prefix at the beginning of the WBS codes for the tasks in the project; for instance, PRJ01.1.4.1.


  2. In the "Code mask" section's first Sequence cell, choose the type of characters you want to use for the top level of the hierarchy, as shown in Figure 1 top.

    You can choose from Numbers (ordered), Uppercase Letters (ordered), Lowercase Letters (ordered), and, for the most flexible coding, Characters (unordered). With ordered numbers and letters, Project automatically increments the numbers or letters as you add tasks to the WBS, proceeding, for example, from 1.1 to 1.2. to 1.3.

  3. In the first Length cell, choose a number (from 1 to 10) for the length of the top level's mask.

    Project initially selects Any, which means the entry for the level can be of any length. If the level uses a number, Project increments the number beginning at 1 and continuing to 10, 100, or 1000, if necessary. If the level uses letters, then you can type a code of any number of characters at that level.

    Choosing a number limits the entry to between one character and the length you specify. If you limit a numeric entry to one character, Project cycles through the numbers 1 through 9, moves to 0, and then repeats.

  4. In the Separator cell, choose the character that separates the top level from the next level.

    Your only choices for separators are periods (.), minus signs (-), plus signs (+), or slashes (/).

  5. Repeat steps 2–4 for each additional level of the code mask.

    You can specify dozens of levels in a code mask (in fact, a WBS code can be as long as 255 characters), but being miserly with levels makes the schedule easier to comprehend.

  6. After you've defined all the levels in the code mask, be sure that the "Generate WBS code for new task" checkbox is turned on if you want Project to automatically assign a WBS code to new tasks you create.

    The only time you might want to turn this checkbox off is when you plan to renumber all the WBS codes after you've organized your tasks and don't want to be distracted by the interim codes that Project assigns.

    To ensure that your WBS codes are unique, keep the "Verify uniqueness of new WBS codes" checkbox turned on. Click OK, and then review the refreshed WBS codes in the task list, as shown in Figure 2. Although Project adds WBS codes to tasks when the "Generate WBS code for new task" checkbox is turned on, sometimes you want to type WBS codes manually, and that can lead to duplicate WBS codes. The only time you might turn off the "Verify uniqueness of new WBS codes" checkbox is if you're planning to renumber tasks later and you get tired of the warnings Project displays. As the box on Renumbering Task WBS Codes explains, you can renumber the WBS codes for tasks to correct or reorder your project.

    Figure 1. Top: The choices for characters, length, and separators are limited. If you use unordered characters, you have to type the characters you want for each code, such as Dsn-.1, Const.3, or Rvw.7.
    Bottom: As you specify the code mask for each level, the "Code preview" box at the top of the dialog box displays a sample WBS code.

  7. If the WBS column isn't visible in the current view, add it so you can verify that the code is set up the way you want.

    Right-click the Task Name heading and, from the shortcut menu, choose Insert Column. In the new column, type WBS and then press Enter.

Congratulations! You've customized your WBS codes.

Figure 2. When you click OK, Project automatically applies the code mask to all the tasks in the schedule.


Workaround Workshop: Renumbering Task WBS Codes

When you customize WBS codes, the "Generate WBS code for new task" checkbox tells Project to automatically assign WBS codes to new tasks you create, whether you insert tasks within the outline or add new tasks at the end. With this setting, as soon as you press Enter to save a new task, the WBS code pops into the WBS cell, maintaining the sequence you've defined. Moving tasks around also adjusts WBS codes and, before you know it, your WBS sequence can be a mess.

The alternative is to turn off this checkbox, and then, after a heated session of adding or modifying the task order, renumber the WBS codes all at once. Fortunately, that's pretty easy to do. When the WBS is the way you want it, do the following:

  1. If you want to renumber only some of the tasks in the Project file, select them.

  2. On the Project tab, click WBS, and then choose Renumber.

  3. In the WBS Renumber dialog box, select the "Entire project" option to renumber all your tasks. If you want to renumber only the selected tasks, choose the "Selected tasks" option instead.

  4. Click OK. Project reapplies the WBS code scheme to the tasks, alphabetizing ordered letters and incrementing ordered numbers.

When you start to build other documents that reference your WBS codes (like work package Word files), you don't want Project to change the existing codes. That's another time to turn off the "Generate WBS code for new task" checkbox. As you type in new WBS codes manually, leave the "Verify uniqueness of new WBS codes" checkbox turned on so Project will warn you if you've duplicated an existing WBS code.

 
Others
 
- Microsoft Project 2010 : Documenting a WBS in Another Program
- Upgrading and Converting to Access 2010 : ENABLING A DATABASE, ACCESS 2010: 64-BIT CONSIDERATIONS
- Upgrading and Converting to Access 2010 : CONVERTING A SECURED DATABASE, CONVERTING A REPLICATED DATABASE
- Microsoft PowerPoint 2010 : Modifying and Formatting SmartArt Graphics
- Microsoft PowerPoint 2010 : Understanding SmartArt Graphics, Inserting Smart Art Graphics
- Microsoft Excel 2010 : Scales of Measurement
- Microsoft Excel 2010 : Variables and Values
- Microsoft Word 2010 : Formatting Paragraphs (part 2) - Working with Tabs, Changing Line Spacing, Adjusting Spacing Between Paragraphs
- Microsoft Word 2010 : Formatting Paragraphs (part 1) - Aligning Text, Adding Paragraph Borders, Shading Text, Indenting Text
- Microsoft Outlook 2010 : Options for Starting Outlook
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us