IT tutorials
 
Office
 

Microsoft Project 2010 : Working with Resources (part 2) - Grouping Resources, Filtering Resources

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
6/1/2013 7:33:43 PM

3. Grouping Resources

You can sort tasks or resources into groups, based on the entries in one or more of the fields, by using the Group By command. For example, you could group resources by resource types (see Figure 5) or by entries in the Group field.

Figure 5. Use the Group By command to sort the resources and organize them into logical groups to simplify the resource views.


Note

Project displays the resource list in outline format by outline code number if you define a custom outline code for resources and use that field for the Group By order.


A difference between sorting and grouping is that in grouping, a Group By record is inserted at the start of each group. Project calculates totals for any numeric fields in this record for the records grouped beneath it. In Figure 8.16, the cost table has been applied and the fields show various measurements of the cost of assignments for the resources. You can see that the total cost of assignments for work resources is $4620.00, whereas the total cost of assignments for material resources is zero. The inserted grouping rows have no resource ID or row number, and they disappear when you remove the grouping.

To group resource records on the resource type as in Figure 5, select the View tab and choose More Groups from the Group by drop-down. Select Work vs. Material Resources. To remove the grouping, choose Project, Group By, No Group, or press Shift+F3.

Tip

If you create a custom outline code for resources—perhaps outlining them geographically by divisions, cities, departments, and job codes—you will find that grouping on that outline field produces a hierarchical outline with rolled-up costs that can be very useful.

If you use a custom text field to identify resource skills, you can insert the Work column in the table and then group by the skills and by start dates to see the total amount of work needed for each skill per week or month. If you insert the Peak column (which shows the maximum number of units assigned for a resource at any moment during a given time period), you could forecast the number of units of a skill that are needed per time period.


You can change the sort order while the resources are grouped. The sort settings are applied within each group. In other words, resources do not move to a different group as a result of the new sort order. The resource list in Figure 8.15 is sorted by cost, in descending order. You can also apply filters while the resources are grouped, which is discussed in the next section.

4. Filtering Resources

Use filters to select all the resources that meet some condition that you specify. For example, you might want to select all your material resources. This condition—that the resource type must be Material—is called the filter criterion. Project has a built-in filter named the Resources–Material filter that implements this criterion for you, as shown in Figure 6.

Figure 6. When the filter is applied, the resources that do not satisfy the selected criteria are hidden from the current view.

After Project selects the resources that meet the criteria, it normally changes the display to show only the selected resources, temporarily hiding all those that do not meet the criteria. However, you can also choose to use a highlight filter, and Project simply highlights the selected resources, without hiding all the others. In Figure 7, the Resources–Material highlight is applied as yellow fill for each row.

Figure 7. The highlighted enables you to continue to display all available resources but highlight the resources that meet the filter criteria.

Tip

Filtering for specific resources is a great way to isolate only the resources that meet specific criteria that you have defined and to temporarily omit the other ones. By doing so, you can save a lot of time by applying a single change that affects an entire group of resources instead of having to change each one independently.



When you finish using the filtered display, you must apply either the [No filter] or [No Highlight] options to return to the normal display, or simply press the F3 key.

Another useful filter for reviewing how you categorized your resources is the Group filter. You can quickly filter the list to show all the resources that have a specific keyword if you have entered keywords in the Group field. For example, if you entered department names in the Group field, you could filter the list for “Design” to identify all the resources that are managed by the Design department. If you used job titles, you could use the filter to isolate resources who might qualify for a certain resource assignment.

Project 2010 lets you filter the list of resources to be displayed in the Assign Resources dialog box. This dialog box is especially useful for substituting one resource for another. Usually, you want to substitute resources that have the same skill set. If you use a custom text field to enter skill keywords, you can filter the resource list to see all resources that might be appropriate substitutes. If you include a comma-separated list of multiple skills, you need to define a special filter for this purpose.

Tip

Project 2010 also lets you use the Assign Resources dialog box to do availability-based scheduling. Highlight a task and check the Available to Work check box, and Project will show you only resources that have a specified amount of availability during the time a task is scheduled. This technique is extremely helpful when trying to find the right people to work on a schedule that has inflexible dates.


You can use filters to quickly check the status of resources after work on the project has begun to see at a glance where problems might lie. The following partial filter listing illustrates how useful filters can be in managing a project and enables you to identify specific categories of resources:

  • Use the Overallocated Resource filter to focus on resources that are assigned to more work than they can possibly finish in the scheduled time period.

  • Use the Cost Overbudget filter to find resources whose scheduled costs are more than you had budgeted.

  • Use the Work Complete filter to find resources that have finished all their work.

  • Use the Slipping Assignments filter to see which resources are taking longer than planned to finish their assignments.

  • Use the Resource/Assignments with Overtime filter to see which resources have been assigned overtime work.


Note

You can apply filters only to full-screen views or views that are in the top pane of a combination view. The bottom-pane views are already filtered for the task or resource that is selected in the top pane. Thus, you cannot apply filters to views in the bottom pane.


You can apply a filter by selecting the View tab. For example, if you want to display only material resources in a resource view, you would follow these steps:

1.
Display one of the resource views that has a table of resources in the top pane.

2.
Click the Filter drop-down to display the drop-down list of resource filters, and then click Resources–Material.

Project hides everything but the resources that have Material in the resource’s Type field.

Tip

To use a filter that is on the menu as a highlight filter, use the Highlight drop-down.

If you have applied a filter and then made changes that might alter which resources are selected by the filter, use Ctrl+F3 to reapply the filter.

 
Others
 
- Microsoft Project 2010 : Working with Resources (part 1) - Setting the Automatically Add New Resources and Tasks Option, Sorting Resources
- Microsoft PowerPoint 2010 : Working with Animation and Transitions - Customizing Animations on the Animation Pane
- Microsoft PowerPoint 2010 : Working with Animation and Transitions - Applying Animation to Objects
- Microsoft Excel 2010 : Collaborating with Colleagues - Protecting Workbooks and Worksheets
- Microsoft Excel 2010 : Collaborating with Colleagues - Tracking and Managing Colleagues’ Changes
- Microsoft Excel 2010 : Collaborating with Colleagues - Managing Comments
- Microsoft Word 2010 : Sharing Word Documents Online - Sharing a Document Through Email
- Microsoft OneNore 2010 : Housecleaning in OneNote - Restoring Pages and Sections from the Recycle Bin
- Microsoft OneNore 2010 : Housecleaning in OneNote - Deleting a Page, Deleting a Section
- Microsoft Outlook 2010 : Manage Scheduling (part 5) - Displaying Different Views of a Calendar
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us