IT tutorials
 
Office
 

Microsoft Project 2010 : Setting Up Resources - Adjusting Working Time for Individual Resources

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
1/14/2012 11:36:37 AM
When you initially create resources in a project plan, Project creates a resource calendar for each work resource. The initial working time settings for resource calendars exactly match those of the project calendar, which by default is the Standard base calendar. The Standard base calendar is built into Project and accommodates a default work schedule from 8 A.M. to 5 P.M., Monday through Friday, with an hour off for lunch each day. If all the working times of your resources match the working time of the project calendar, you do not need to edit any resource calendars. However, chances are that some of your resources will need exceptions to the working time in the project calendar—such as
  • A flextime work schedule

  • Vacation time

  • Other times when a resource is not available to work on the project, such as time spent training or attending a conference

Tip

If you have a resource who is available to work on your project only part time, you might be tempted to set the working time of the resource in your project to reflect a part-time schedule, such as 8 A.M. to 12 P.M. daily. However, a better approach would be to adjust the availability of the resource as recorded in the Max. Units field to 50%, as you did for the previous exercise for the resource named Sharon Salavaria. Changing the unit availability of the resource keeps the focus on the capacity of the resource to work on the project rather than on the specific times of the day when that work might occur. You set the maximum units for a resource in the Resource Sheet view.

Changes that you make to the project calendar are reflected automatically in resource calendars derived from the same project calendar.

In this exercise, you specify the working and nonworking times for individual work resources.

  1. On the Project tab, in the Properties group, click Change Working Time.

    Tip

    The Change Working Time dialog box appears.

  2. In the For calendar box, click Toby Nixon.

    Toby Nixon’s resource calendar appears in the Change Working Time dialog box. Toby has told you he will not be available to work on Thursday and Friday, January 19 and 20, because he plans to attend a book industry conference.

  3. On the Exceptions tab in the Change Working Time dialog box, click in the first row directly below the Name column heading and type Toby attending a conference.

    The description for the calendar exception is a handy reminder for you and others who may view the project plan later.

  4. Click in the Start field and type or select 1/19/12.

  5. Click in the Finish field, type or select 1/20/12, and then press the Enter key.

    Tip

    Alternatively, in the calendar you can first select the date or date range for which you want to create an exception, and then enter the exception name. Project will insert the Start and Finish dates automatically based on your selection, and then press the Enter key.

    Tip

    Project will not schedule work for Toby on these dates.

    Tip

    To set up a partial working time exception for a resource, such as a portion of a day when a resource cannot work, click Details. In the Details dialog box, you can also create recurring exceptions to the resource’s availability.

    To conclude this exercise, you will set up a "4 by 10" work schedule (that is, 4 days per week, 10 hours per day) for a resource.

  6. In the For box, click Jun Cao.

  7. When prompted to save the resource calendar changes that you made for Toby Nixon, click Yes.

  8. Click the Work Weeks tab in the Change Working Time dialog box.

  9. Click [Default] directly under the Name column heading, and then click Details.

    Next, you will modify the default working week days and times for Jun Cao.

  10. Under Selected Day(s), select Monday through Thursday.

    These are the weekdays Jun can normally work.

  11. Click Set day(s) to these specific working times.

    Next you’ll modify Jun’s regular daily schedule for the days she normally works.

  12. In row 2, click 5:00 PM and replace it with 7:00 PM, and then press Enter.

    Finally, you will mark Friday as a nonworking day for Jun.

  13. Click Friday.

  14. Click Set days to nonworking time.

    Now Project can schedule work for Jun as late as 7 P.M. every Monday through Thursday, but it will not schedule work for her on Fridays.

    Tip
  15. Click OK to close the Details dialog box.

    You can see in the calendar in the Change Working Time dialog box that Fridays (as well as Saturdays and Sundays) are marked as nonworking days for Jun Cao.

    Tip
  16. Click OK to close the Change Working Time dialog box.

    Because you have not yet assigned these resources to tasks, you don’t see the scheduling effect of their nonworking time settings.

    Tip

    If you find that you must edit several resource calendars in a similar way (to handle a night shift, for example), it may be easier to assign a different base calendar to a resource or collection of resources. This is more efficient than editing individual calendars, and it allows you to make project-wide adjustments to a single base calendar if needed. For example, if your project includes a day shift and a night shift, you can apply the Night Shift base calendar to those resources who work the night shift. You change a base calendar in the Change Working Time dialog box. For collections of resources, you can select a specific base calendar directly in the Base Calendar column on the Entry table in the Resource Sheet view.

 
Others
 
- Microsoft Project 2010 : Setting Up Resources - Entering Resource Pay Rates
- Microsoft Visio 2010 : Displaying the rule for a selected issue
- Accessing PowerPoint on the Web and Mobile Devices (part 2) - Setting SkyDrive Permissions
- Accessing PowerPoint on the Web and Mobile Devices (part 1) - Setting Up SkyDrive
- Microsoft PowerPoint 2010 : Managing Themes
- Microsoft Excel 2010 : Printing in Excel - Adjusting Page Margins & Inserting Page Breaks
- Microsoft Excel 2010 : Setting the Print Area
- Microsoft Outlook 2010 : Setting Up Mobile Alerts for Important Messages
- Microsoft Outlook 2010 : Setting Up Calendar Alerts
- Microsoft OneNote 2010 : Searching for Stray Notes (part 2)
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us