IT tutorials
 
Office
 

Microsoft Project 2010 : Formatting and Sharing Your Plan (part 1) - Customizing the Gantt Chart View

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
5/13/2013 3:53:25 AM

1. Customizing the Gantt Chart View

The Gantt chart became a standard way of visualizing project plans when, in the early 20th century, American engineer Henry Gantt developed a bar chart showing the use of resources over time. For many people, a Gantt chart is synonymous with a project plan. In Project, the default view is the Gantt Chart view. You are likely to spend a lot of your time in this view when working in Project.

The Gantt Chart view consists of two parts: a table on the left and a bar chart on the right. The bar chart includes a timescale band across the top that denotes units of time. The bars on the chart graphically represent the tasks in the table in terms of start and finish dates, duration, and status (for example, whether work on the task has started or not). Other elements on the chart, such as link lines, represent relationships between tasks. The Gantt chart is a popular and widely understood representation of project information throughout the project management world.

Tip

By default, Project displays a split view named Gantt with Timeline when you start the program. However, you can change this setting to display any view you want at startup. On the File tab, click Options. In the Project Options dialog box, click General. In the Default View box, click the view you want. The next time you start Project and create a new project plan, the view you have chosen will appear.

The default formatting applied to the Gantt Chart view works well for onscreen viewing, sharing with other programs, and printing. However, you can change the formatting of almost any element on the Gantt chart.

There are three distinct ways to format Gantt bars:

  • Quickly apply predefined color combinations from the Gantt Chart Style group, which you can see on the Format tab when a Gantt Chart is displayed.

  • Apply highly customized formatting to Gantt bars in the Bar Styles dialog box, which you can open by clicking the Format tab when a Gantt chart is displayed, then, in the Bar Styles group, click Format, Bar Styles. In this case, the formatting changes you make to a particular type of Gantt bar (a summary task, for example) apply to all such Gantt bars in the Gantt chart.

  • Format individual Gantt bars directly. The direct formatting changes that you make have no effect on other bars in the Gantt chart. You can double-click a Gantt bar to view its formatting options, or, on the Format tab in the Bar Styles group, click Format, Bar. 

In this exercise, you change the formatting of the Gantt chart view.

  1. On the File tab, click Save As.

    Project displays the Save As dialog box.

  2. In the File name box, type Simple Formatting, and then click Save.

    To begin, you will display the project summary task to see the top-level or rolled-up details of the project. Project automatically generates the project summary task but doesn’t display it by default.

  3. On the Format tab, in the Show/Hide group, click Project Summary Task.

    Project displays the project summary task at the top of the Gantt Chart view.

    Set Up

    The project summary task, which is always numbered as task 0, contains top-level information such as duration, work, and costs for the entire project. The name of the project summary task comes from the title entered in the plan’s advanced properties in the Backstage view, or if that is blank, Project uses the file name as the project summary task’s name.

    Next, you will adjust the colors of the Gantt bars and milestones in the chart portion of the Gantt Chart view. You’ll begin by viewing the Gantt bar for a manual task so you can see how it is affected by the Gantt bar formatting.

  4. In the Task Name column, click the name of task 9, Prepare book P&L statement.

    Set Up
  5. On the Task tab, in the Editing group, click Scroll to Task.

    Tip

    You can accomplish the same thing by right-clicking the task name and in the shortcut menu that appears, clicking Scroll To Task.

    Project scrolls the chart portion of the Gantt Chart view to display the Gantt bar for a manually scheduled task that was previously added to the book launch plan.

    Tip

    Keep an eye on this Gantt bar as we apply a different Gantt Chart style to the project plan.

  6. On the Format tab, in the Gantt Chart Style group, click More to display the predefined color styles.

    Tip

    More

    Tip

    The Gantt Chart styles are divided into two groups:

    • Scheduling Styles distinguish between manually and automatically scheduled tasks.

    • Presentation Styles do not.

  7. Under Presentation Styles, click the orange color scheme.

    Project applies this style to the Gantt bars in the project plan.

    Tip

    The Gantt bar of task 9, the manually scheduled task, is no longer visually distinct from the automatically scheduled tasks.

    Applying a presentation style to the Gantt Chart view is an option that you can use when you don’t want to distinguish between manual and automatically scheduled tasks—when showing the Gantt chart to an audience for whom you do not want to make this distinction, for example.

    Your next step in this exercise is to reformat a task name so it will visually stand out.

  8. In the Task Name column, right-click the name of task 6, Planning Complete!

    This is a milestone task that describes the end of the first phase of the new book launch at Lucerne Publishing. You’d like to highlight this task name.

    Tip

    In addition to the regular shortcut menu, note the mini-toolbar.

  9. On the mini-toolbar, click the arrow next to the Background Color button, and under Standard Colors, click yellow.

    Tip

    Background Color

    Tip

    You can also click the Task tab, and in the Font group, click Background Color.

    Project applies the yellow background color to the task name’s cell.

  10. Right-click the task name again, and on the mini-toolbar, click the Italic button.

    Italic
    Tip

    Now the milestone name stands out. You can also format the milestone indicator in the chart. You’ll do this next.

  11. On the Format tab, in the Bar Styles group, click Format and then click Bar.

    Tip
  12. In the Format Bar dialog box, under Start, click the Shape drop-down list.

    Project displays the symbols you can use as a Gantt bar edge, or, in this case for a milestone, as a milestone symbol.

    Tip
  13. Click the star symbol, and then click OK.

    Project uses the star symbol as the milestone symbol for this task.

    Tip

    Tip

    In this exercise, you used the Bar command to format a single Gantt bar. You can also customize entire categories of Gantt bars, such as all milestones, via the Bar Styles command. 

    To conclude this exercise, you will add horizontal gridlines to the chart portion of the Gantt Chart view so you can more easily associate Gantt bars with their tasks.

  14. On the Format tab, in the Format group, click Gridlines, and then click Gridlines.

    Tip
  15. Under Lines to change, leave Gantt Rows selected, and in the Type box under Normal, select the small dashed line (the third option down), and then click OK.

    Project draws dashed lines across the chart portion of the Gantt Chart view.

    Tip
 
Others
 
- Microsoft PowerPoint 2010 : Setting Tabs and Indents
- Microsoft PowerPoint 2010 : Formatting Numbered Lists
- Microsoft PowerPoint 2010 : Formatting Bulleted Lists
- Microsoft Excel 2010 : Collaborating with Colleagues - Sharing Workbooks
- Microsoft Excel 2010 : Inserting WordArt, Inserting Pictures
- Microsoft Word 2010 : Creating Form Letters with Mail Merge - Finishing the Merge
- Microsoft Word 2010 : Creating Form Letters with Mail Merge - Inserting Merge Fields
- Microsoft Word 2010 : Creating Form Letters with Mail Merge - Creating the Main Document, Specifying Data for Your Mail Merge
- Microsoft OneNore 2010 : Sharing Notebooks with Others (part 2) - Finding Notes by Specific Authors, Finding Recently Edited Notes
- Microsoft OneNore 2010 : Sharing Notebooks with Others (part 1) - Sharing a Notebook, . Finding Unread Notes
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us