IT tutorials
 
Office
 

Microsoft Project and the Project Management Domain : Exploring Project Management Industry Standards

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
4/25/2013 2:56:34 AM

Anyone can create a file using Microsoft Project. Organizing that file into a logical flow of work, however, requires a solid understanding of how projects should be managed and decomposed into logical units. To understand project management, you must understand the standards and methodology behind it. Although Gantt Charts and other similar resources are used in almost all project management schedules, there are several different ways of using those resources.

Project Management Body of Knowledge (PMBOK)

The Project Management Institute, or PMI, is an internationally recognized organization that has developed standards for the domain of project management including standards for portfolio management, program management, project management, and Work Breakdown Structures. PMI has several hundred thousand members in more than 65 countries.

The standards created by PMI are authored by a vast network of project management professionals who volunteer their time to create and update these standards on a regular basis. The standards groups are from many different countries across the globe; they research topics and collaborate to bring together the latest thinking and techniques from their collective experience.

Tip

PMI makes a clear distinction between a project plan and a project schedule. The plan is a formal document that includes narrative on communication approaches, assumptions, deliverables, and execution of the project. The schedule is one component of the plan that focuses on the timeline for the activities to be performed. As scheduling tools become more sophisticated, they are gradually including more elements that used to reside only in the plan. Microsoft Project Desktop still focuses on scheduling functions, but the server components have added capabilities to support more of the plan functions.


The PMBOK Guide has established five process groups to define the project management process. These processes are as follows:

  • Initiating Process Group— Defines and authorizes the project or a project phase.

  • Planning Process Group— Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project is to address.

  • Executing Process Group— Integrates people and other resources to carry out the project management plan.

  • Monitoring and Controlling Process Group— Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.

  • Closing Process Group— Formalizes acceptance of the product, service, or result and brings the project or a project phase to an orderly end.

Projects are created and implemented in environments that are larger in scope than the projects themselves. All projects must have a beginning and an end, as shown by the Initiating and Closing Process Groups. In between, a project will be engaged continually with the other three process groups, as shown in Figure 1.

Figure 1. The relationship among the PMBOK process groups (taken from Figure 3-4, PMBOK Guide, Third Edition).

The PMBOK identifies nine knowledge areas that a project manager should consider throughout the entire life cycle of a project. Knowledge areas focus on a specific aspect of the overall domain and identify the elements that need to be considered to properly manage a project:

  • Project Integration Management— This knowledge area looks at the processes and activities that are needed to identify, define, combine, unify, and coordinate the different actions within a Project Management Process Group.

  • Project Scope Management— This knowledge area handles scope planning, scope definition, creating a WBS (decomposition of the scope into smaller components), scope verification, and scope control.

  • Project Time Management— This knowledge area concerns five different steps: activity definition, activity sequencing, activity resource estimating, activity duration estimating, and schedule development.

  • Project Cost Management— This knowledge area involves planning, estimating, budgeting, and controlling costs so a project can be finished within budget.

  • Project Quality Management— This knowledge area determines policies, objectives, and responsibilities to meet a project’s quality standards.

  • Project Human Resource Management— This knowledge area helps organize and manage a project’s team, the people necessary for the completion of the project.

  • Project Communications Management— This knowledge area involves the processes that ensure timely generation, collection, distribution, storage, retrieval, and disposition of information.

  • Project Risk Management— This knowledge area envelopes risk management planning, identification, analysis, responses, monitoring, and controlling of a project.

  • Project Procurement Management— This knowledge area involves the processes necessary to purchase products, services, or results from outside the project team.


The nine knowledge areas are specifically designed to work with the five process groups to identify possible areas for management within the scope of the project. They are referred to here as the “5×9 checklist.” When the two components are combined, they provide guidance for what elements should be considered at what time in a project. In the context of the MSP desktop, the key knowledge areas are scope, time, and cost. These components will help you build the initial project schedule framework. All the other knowledge areas will play a part in building the working baseline schedule, and it is recommended that each be considered in the context of the framework. For example, the resources to be applied to a project might involve both the Project Human Resource Management and the Project Procurement Management knowledge areas. Until you have a general idea of the scope, expected timeframes, and budget for that work, however, you will not be able to identify which area is most appropriate. The emphasis for each knowledge areas varies by phase of project; some will be more important in one phase than another, but all of the nine are used throughout the project.

PRINCE2

PRINCE2, which stands for Projects in Controlled Environments, is a project management methodology developed by the United Kingdom government. It is in its second release and was originally known as the PRINCE technique. The first release was established in 1989 by the Central Computer and Telecommunications Agency (CCTA) as a standard for information technology project management. Because of its success in IT, the methodology was republished about seven years later in a version that could be applied across many other disciplines. PRINCE2 was again updated in 2005 by the Office of Government Commerce (OGC), has become the standard for project management in the UK, and is now used in 50 other countries. You can become certified in the use of PRINCE2 at either one of two levels: Foundation and Practitioner.

PRINCE2 uses a simple four-step process to explain what each project will need, as shown in Figure 2. This process is explained in more detail using the following eight different processes, sometimes known as the Validation, Quality, Verification, and Approval steps:

  • Start-up— This is when a project manager is chosen. The need for the project is defined and outlined as to how it will be executed.

  • Direction— The project manager, who reports to the Project Board, is responsible for managing the details. The Project Board is responsible for the overall success of the current project and defines the direction in which the project will be heading.

  • Initiation— The Project Initiation Document is prepared and submitted to the Project Board for approval and possible revision.

  • Stage Control— During this stage, the project is broken down into several different manageable stages. The number of stages depend on the size and risk level of the project, and each stage must also plan for the succeeding stage. Before any new stage can begin, the current stage must be fully finished.

  • Stage Boundary Management— At this stage, the Project Board must review the current stage and then develop the process for the next stage. It is only after the approval for the execution of the current stage and the planning of the next stage that the project can continue.

  • Planning— This stage is used for deciding what products will be produced and what is required for their production. Then, estimates are made for cost, time, and any other resources, plus any risk analysis, activity scheduling, and process streamlining that is necessary for the project.

  • Product Delivery Management— This is the production stage, where the project manager confirms that the right goods are being produced correctly and on schedule.

  • Closing— After everything is finished, the project manager must perform a post-project review, which evaluates the outcome of the project. When this review is approved by the Project Board, the project is complete.

Figure 2. The PRINCE2 four-step process.

Note

There is no conflict between PMBOK and PRINCE2. They can be used together if a project manager chooses to use both. PRINCE2 is a methodology and focuses more on deliverables, whereas PMBOK is a standard and focuses on the process and knowledge areas. PRINCE2 establishes a Validation of Process (through a very specific focus on deliverables and the activities around them), whereas PMBOK focuses on the processes used to manage the deliverables.


In addition to consideration of these standards and methods, project managers need to understand the environment in which they will be working before they create a schedule. They need to be aware of the various methodologies and approaches that can be used to help them (or confuse them, if they do not understand how and when the methodologies and approaches should be applied). The following section provides an introduction to this information.

 
Others
 
- Microsoft OneNote 2010 : Formatting Text (part 2) - Inserting Symbols and Special Characters, Copying and Applying Formatting with the Format Painter
- Microsoft OneNote 2010 : Formatting Text (part 1) - Setting the Default Font, Changing Basic Text Formatting, Using the Styles Gallery
- Microsoft Visio 2010 : Managing and Styling Pages (part 3) - Controlling Page Size and Orientation, Setting Page Scales
- Microsoft Visio 2010 : Managing and Styling Pages (part 2) - Working with Background Pages, Inserting Backgrounds, Titles, and Borders
- Microsoft Visio 2010 : Managing and Styling Pages (part 1) - Inserting Pages
- Microsoft PowerPoint 2010 : Incorporating Motion Video - Specifying Playback Options
- Microsoft PowerPoint 2010 : Managing Videos Between PCs and PowerPoint Versions, Changing the Video's Formatting
- Microsoft Excel 2010 : Macros and UDFs - User-Defined Functions
- Microsoft Excel 2010 : Macros and UDFs - Running a Macro
- Microsoft Word 2010 : Proofing a Document - Using Word's Research Tools
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us