Because a project involves a myriad of tasks,
resources, assignments, dates, and more, it’s obvious that you need some
kind of tool to help you track the details. By using a spreadsheet or a
word-processing program, you could create a table that lists your
tasks, durations, start and finish dates, and assigned resources. In
fact, that might very well get you started. But it’s likely that you’ll
end up working harder than you have to in an attempt to make the tool
work right, especially when changes have to be made during the project.
Such a table would not be able to:
Calculate the start and finish dates for you. Indicate whether assigned resources are actually available. Inform you if assigned resources are underallocated or overworked. Alert you if there’s an upcoming deadline. Understand how much material you’ve depleted or how much you’re spending on supplies and services. Calculate how much of the budget you’ve spent so far. Draw your project tasks as a Gantt chart or network diagram so you can visualize your project.
To do this and more, you can
create a table in Project 2010. You can then use the project database,
schedule calculation, and charting capabilities to help facilitate your
project management processes, as shown in Figure 1.
Although Project 2010
can’t negotiate a more reasonable finish date, it can help you determine
what you have to sacrifice to make that date. Although Project 2010
won’t complete a difficult and time-consuming task for your team, it
will help you find extra time in the schedule or additional resources
for that task. And although Project 2010 can’t motivate an uninspired
team member, it can tell you if that team member is working on critical
tasks that will affect the finish date of the entire project.
In short, Project 2010 can
help you facilitate all processes in the project management life cycle,
from developing your scope, modeling your project schedule, and tracking
and communicating progress, to saving knowledge gained from the closed
project. Furthermore, with Microsoft Project Professional 2010, project
management standards can be established and disseminated throughout your
enterprise.
1. Creating a Model of Your Project
You can use Project 2010 to
create a model of your project. This model reflects the reality of your
project. You enter your tasks, resources, assignments, and other
project-related information into Project 2010. You can then organize and
manage the copious and very detailed bits of project information that
otherwise can be quite overwhelming.
With all the
necessary information stored in Project 2010, the exact project
information you need at any given time is always at your fingertips. You
can manipulate and analyze this information in various ways to solve
problems, make decisions, and communicate progress to successfully
manage the project. As you take action and move forward in your project,
you update information in Project 2010 so that it continues to reflect
reality. (See Figure 2.)
1.1. Planning with Project 2010
Specifically, in the planning stage, you use Project 2010 to do the following:
Create your project phases, milestones, and task list
Project 2010 uses your task list as the basis for the project database
it creates for you. You can organize tasks within phases or subtasks
within summary tasks so that you can break your project down into
manageable segments. Estimate task durations One
task might take two hours to complete; another might take four days.
Unless you’re scheduling manually, Project 2010 uses these durations to
help build your schedule. Link tasks with their appropriate relationships to other tasks
Often, a task cannot begin until a previous task has been completed.
For example, for an office move project, you schedule the “Design office
space” task before the “Order new furniture” task. The two tasks are
linked because the second task cannot be done until the first task is
complete. Unless you’re using manual scheduling, Project 2010 uses these
task relationships to build your schedule. The durations and task
relationships are also shown in the Gantt Chart and Network Diagram
views of your project. Enter any imposed deadlines or other date constraints
If you know that you must vacate your current office space by the end
of August, for example, you work with that date as one of the important
constraints of your project. Project 2010 can automatically schedule
according to such constraints and inform you of a conflict between a
constraint and the durations or task relationships you have also set. Set up the resources and assign them to tasks
Resources can be employees, vendors, or equipment that are responsible
for carrying out tasks. Not only does Project 2010 keep track of which
resources are assigned to which tasks, it also schedules work on
assignments according to the resource’s availability and lets you know
whether a resource is overloaded with more tasks than can be
accomplished in the resource’s available time. Resources can also
include materials consumed or special costs incurred in the execution of
a task, so you can plan for how much lumber you need, for example, or
how much you’re going to have to spend on travel costs throughout the
life of the project. Establish resource costs and task costs
You can specify hourly, monthly, or peruse rates for the employees or
equipment being used to complete tasks. You can specify the cost for
consumable materials or other special costs for items such as trade show
registration, printing, or travel. When your human, equipment,
material, and cost resources are assigned to tasks, Project 2010
calculates and adds these costs so that you can get an accurate view of
how much your project will cost to execute. You can often use this
calculation as a basis for the project budget. Adjust the plan to achieve a targeted finish date or budget amount
Suppose that your project plan initially shows a finish date that’s two
months later than required or a cost that’s $10,000 more than the
allocated budget. You can make adjustments to scope, schedule, cost, and
resources to bring the project plan in line. While working through your
inevitable project tradeoffs, Project 2010 can recalculate your
schedule automatically until you have the result you need.
1.2. Executing with Project 2010
In the execution stage of
the project, planning is complete and you give the green light for the
project team members to start work on their assigned tasks.
Communication is a huge part of the execution stage. Use Project 2010 to
communicate in one or more of the following ways:
Print to-do lists You can print a to-do list for each team member, or print a report of tasks coming due within the next month.
Send e-mail messages containing task lists
You can send task lists to team members over e-mail. If they use
Microsoft Outlook or another MAPI-based e-mail program, they can
integrate the items into their e-mail task list.
Communicate task assignments and progress with your SharePoint workgroup Use Microsoft SharePoint 2010 to post task lists and updates for communication and collaboration among your team members.
Communicate task information with Microsoft Project Server 2010
Use the power of enterprise project management and Microsoft Project
Web App to exchange task and progress information with team members.
1.3. Monitoring and Controlling with Project 2010
In the execution and control stage of the project, use Project 2010 to do the following:
Save the baseline plan
For comparison and tracking purposes, you need to take a snapshot of
what you consider your baseline project plan. As you update task
progress through the life of the project, you can compare current
progress with that snapshot of your original plan. These comparisons
provide valuable information about whether you’re on track with the
schedule and your budget. Update actual task progress With
Project 2010, you can update task progress by entering percentage
complete, work complete, work remaining, and more. As you enter actual
progress, the schedule can be automatically recalculated. Compare variances between planned and actual task information
Using the baseline information you saved, Project 2010 presents various
views to show your baseline against actual and scheduled progress,
along with any variances. For example, if your initial project plan
shows that you had originally planned to finish a task on Thursday, but
the resource actually finished it on Monday, you’d have a variance of
three days in your favor. Review planned, actual, and scheduled costs
In addition to seeing task progress variances, you can compare baseline
costs against actual and currently scheduled costs and see the
resulting cost variances. Project 2010 can also use your baseline and
current schedule information for earned value calculations that you can use for more detailed analyses. Adjust the plan to respond to changes in scope, finish date, and budget
What if you get a directive in the middle of the project to cut $10,000
from your budget? Or what if you learn that you must bring the project
in a month earlier to catch a vital marketing window? Even in the midst
of a project, you can adjust scope, schedule, cost, and resources in
your project plan. With each change you make, Project 2010 can
recalculate your schedule automatically.
Report on progress, costs, resource utilization, and more
Using the database and calculation features of Project 2010, you can
generate a number of text-based and visual reports. For example, reports
can show the project summary, milestones, tasks starting soon,
over-budget tasks, resource to-do lists, and other information. The
visual reports send Project 2010 data to Microsoft Excel 2010 or Visio
2010, which lets you see the data as a column chart or flow diagram, for
example. You can modify these built-in reports to suit your needs or
create custom reports entirely from scratch.
1.4. Closing with Project 2010
In the closing stage of the project, use Project 2010 to accomplish the following tasks:
Capture actual task duration metrics
If you tracked task progress throughout the project, at the end of the
project you have solid, tested data for how long certain tasks actually
take. Capture successful task sequencing
Sometimes, you’re not sure at the outset of a project whether a task
should be performed sooner or later in the cycle. With the experience of
the project behind you, you can see whether your sequencing worked
well. Save a template for the next project of this kind
Use your project plan as the boilerplate for the next project. You and
other project managers will have a task list, milestones, deliverables,
sequence, durations, and task relationships already in place, and this
template can easily be modified to fit the requirements of the new
project.You can also use Project
2010 to work with multiple projects—and even show the task or resource
links among them. In the course of modeling your project in this way,
Project 2010 serves as your project information system. Project 2010
arranges the thousands of bits of information in various ways so that
you can work with it, analyze your data, and make decisions based on
coherent and soundly calculated project management information. This
project information system carries out three basic functions:
It stores
project information, including tasks, resources, assignments, durations,
task relationships, task sequences, calendars, and more. If
you so choose, it calculates information such as dates, schedules,
costs, durations, critical path, earned value, variances, and more. It
presents views of information you’re retrieving. You can specify the
views, tables, filters, groups, fields, or reports, depending on what
aspect of your project model you need to see.
2. Working with Your Team Through Project 2010
In addition to helping you
create your project plan, Project 2010 helps with resource management,
cost management, and team communications. With Project 2010 resource
management features, you can perform the following tasks:
Enter resources in the Project 2010 resource list. Enter resources from your organization’s e-mail address book, Active Directory service, or Project Server 2010 accounts. Maintain a reusable pool of resources available across multiple projects. Specify skills required for a task and have Project 2010 search for available resources with those skills. Schedule tasks according to the availability of assigned resources. See
which assignments all resources are working on, and also identify
resource overload or underutilization at a glance and make adjustments
accordingly. Book a proposed resource in your project (using Project Professional 2010).
With the cost management features of Project 2010, you can do the following:
Enter periodic or per-use costs for human, equipment, and material resources, including multiple rates for different task types. Enter costs for fees, supplies, or services that will be incurred on a task; for example, permit fees or travel costs. Enter fixed costs for tasks. Estimate costs for the project while the project is still in the planning process. Compare planned cost variances to actual cost variances. Compare planned, actual, or scheduled costs against your budget. View cost totals for tasks, resources, phases, and the entire project. Analyze
earned value calculations, including budgeted cost of work performed
(BCWP), schedule variance (SV), and earned value (EV).
Your communications requirements
might be as simple as printing a Gantt chart or resource list for a
weekly status meeting. Or you might prefer to electronically exchange
task updates with your resources every day and publish high-level
project information to your company’s intranet.
With Project 2010, you can communicate with others in just the way you need, as follows:
Print a view as it looks on your screen. Generate and print a predesigned text-based report. Generate and print a predesigned visual report by using Project 2010 data in Excel or Visio 2010. Create a custom view, text-based report, or visual report. Copy a project view as a static picture to another Microsoft Office application.
Being able to
collaborate summary and detailed project information with team members
and project stakeholders is essential, whether or not you’re using
enterprise capabilities.
Use SharePoint 2010 to collaborate with your team by posting and synchronizing task lists as well as making project updates. Exchange task assignments, updates, and status reports with your team members through Project Server and Project Web App. Allow team leads to delegate tasks to other team members. Track issues and documents through SharePoint Server, Project Server, and Project Web App. Publish
the project through Project Server and Project Web App for review by
team members, senior management, customers, and other stakeholders.
3. Using Project 2010 in Your Enterprise
Through the use of
Project Server, as accessed by Project Professional and Project Web App,
an entire portfolio of projects can be standardized across your
enterprise. Numerous Project 2010 elements, including views, filters,
groups, fields, and formulas, can be designed and included in the
enterprise global template that reflects your organization’s specific
project management methodology. This customization and design is done by
a project server administrator. This project server administrator is the person who sets up and manages
the installation of Project 2010 for your organization. The project
server administrator knows the requirements of project management and
the features of Project 2010 well enough to design custom solutions and
is often a programmer or other information technology professional. The
project server administrator might also be a technically oriented lead
project manager.
When your project
server administrator designs a common enterprise project template, all
project managers in the organization can then work with the same
customized project elements that support organizational initiatives. In
addition, senior managers can review summary information from multiple
projects throughout the organization.
The project server administrator also sets up the enterprise resource pool,
which contains all the resources available to the enterprise, and from
which the various project managers draw to staff their projects. The
enterprise resource pool includes key resource information such as cost,
availability, and skill set.
Some organizations might divide the duties between a project server administrator and portfolio manager.
The project server administrator can handle installation, server,
network, and database issues, and the portfolio manager can be
responsible for designing custom project elements, managing the
enterprise resource pool, and setting up users and permissions.
|