IT tutorials
 
Office
 

Microsoft Project 2010 : Maintaining Baselines (part 3) - Resetting a Baseline , Multiple Baselines

- Free product key for windows 10
- Free Product Key for Microsoft office 365
- Product Key Free : Microsoft Office 2019 – Serial Number
3/30/2014 2:19:56 AM

4. Resetting a Baseline

At any time, you can reset the baseline. When you do this, the old baseline values disappear and are replaced with whatever values are in your current Finish, Start, Duration, Work, and Cost fields. The old baseline values are lost, unless you choose to save multiple baselines.

To reset the baseline, follow these steps (see Figure 5):

  1. Select Project tab => Schedule group => Set Baseline => Set Baseline.

  2. In the Set Baseline dialog box, Set Baseline is selected by default (with the date the baseline was last saved in parentheses). The For: Entire Project option is also selected by default. Click OK.

  3. A "Baseline has already been used" message appears. Click Yes.

The baseline has now been reset. A new date is now associated with the baseline and will appear in the Set Baseline field in the Set Baseline dialog box the next time you access it.

Figure 5. Resetting a baseline

5. Multiple Baselines

You can keep multiple baselines for a project. Project allows you to maintain up to 10 baselines plus the core baseline. This comes in handy when you have a major change in scope—enough to warrant a baseline reset (a change significant enough to change the original agreement or intent of the project deliverables).

Another common occurrence is project reprioritization. Perhaps you started your project, but part way through, it was put on hold and pushed out to the future. When this occurs, and you restart the project, it may be necessary to reset the baseline. Instead of erasing the original baseline, you can save it to another of the baseline options.

Save the Interim Plan-Keep the Core Baseline Current

I recommend that you save an interim baseline into baselines 1, 2, 3, and so on before you reset your baseline. This allows you to keep the core (or original) baseline as the current baseline. This is important, because all the custom views, tables, filters, and earned value formulas default to using the core baseline values, not baseline 1 or baseline 2 or other baseline values.


To take advantage of the multiple-baseline option, you should follow a two-step process: first, save an interim plan; second, reset the core baseline. This way, your current baseline is always in the core baseline values; you have backed-up baselines in the baseline 1 through 10 values, depending on how many times you reset the baseline.

To save a backup or an interim baseline plan, follow these steps (see Figure 6):

  1. Select Project tab => Schedule group => Set Baseline drop-down list => Set Interim Plan.

  2. In the Set Baseline dialog box, select Baseline from the Copy drop-down list.

  3. Select Baseline 1 from the Into drop-down list. (For the second backup, select Baseline 2, and so on.)

  4. For: Entire Project is selected by default. Click OK.

You've now backed up, or saved, your core baseline into the baseline 1 fields. You can repeat this process the next time you want to reset the baseline, but copy it into baseline 2, and so on. Saving an interim plan doesn't reset the baseline, nor does it change the baseline data in the view you've applied.

After you save an interim baseline plan, you can safely reset the baseline without losing the original baseline data, because that information is stored in the baseline 1 fields. To reset the baseline, follow the steps associated with Figure 6.

The Tracking Gantt view is formatted to display only the core baseline values and not baseline 1 through baseline 10 values. To view multiple baselines in the Gantt chart, select the multiple-baselines view, shown in Figure 7, as follows:

  1. Select View tab => Task Views group => Gantt Chart drop-down list => More Views.

  2. In the More Views dialog box, click Multiple Baselines Gantt.

  3. Click Apply.

Figure 6. Saving an interim baseline plan

Figure 7. Viewing multiple baselines in the Gantt chart

Each baseline is represented by a separate colored line in the Gantt chart, as shown in Figure 7. You can add any of the baseline 1 through baseline 10 fields to any table, create your own Variance fields using the other baseline fields, or add other baseline bars in the Gantt bar area by reformatting the bar styles.

Setting a Baseline on Manually Scheduled Tasks

If you set a baseline for manually scheduled tasks that don't have start date, duration, or finish date information, and the field is left blank, then the baseline information is blank as well. In other words, the baseline fields are also manually adjustable. However, the start and finish dates are internally recorded as the current date. So, if you later enter dates for a manually scheduled task, you still get a calculated variance. You can also manually enter different baseline information, and Project uses that to calculate variance. If you have text in the Start, Duration, or Finish field, it's copied into the baseline fields as well.

This also impacts how the variance is calculated, because the behavior is different depending on the values in each field. If you have incomplete schedule data for manually scheduled tasks, then setting the baseline and analyzing variance calculations won't be very useful.

 
Others
 
- Microsoft Project 2010 : Maintaining Baselines (part 2) - Rolling-Wave Planning with Baselines
- Microsoft Project 2010 : Maintaining Baselines (part 1) - Clearing a Baseline
- Microsoft Project 2010 : Viewing Baselines (part 2) - Formatting the Gantt Chart to Display the Baseline
- Microsoft Project 2010 : Viewing Baselines (part 1) - Tracking Gantt View and the Variance Table
- Microsoft Project 2010 : Understanding and Setting Baselines
- Microsoft Project 2010 : Strategic Importance of Project 2010
- Microsoft PowerPoint 2010 : Animating a SmartArt Graphic (part 2) - Apply a Customized Animation to a SmartArt Graphic, Reverse the Order of a SmartArt Graphic Animation
- Microsoft PowerPoint 2010 : Animating a SmartArt Graphic (part 1) - Animate a SmartArt Graphic
- Microsoft PowerPoint 2010 : Coordinating Multiple Animations (part 2) - Set Time Between Animations,Modify an Animation
- Microsoft PowerPoint 2010 : Coordinating Multiple Animations (part 1) - Work with Multiple Animations, Modify the Animation Order
 
 
Top 10
 
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 2) - Wireframes,Legends
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Finding containers and lists in Visio (part 1) - Swimlanes
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Formatting and sizing lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Adding shapes to lists
- Microsoft Visio 2013 : Adding Structure to Your Diagrams - Sizing containers
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 3) - The Other Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 2) - The Data Properties of a Control
- Microsoft Access 2010 : Control Properties and Why to Use Them (part 1) - The Format Properties of a Control
- Microsoft Access 2010 : Form Properties and Why Should You Use Them - Working with the Properties Window
- Microsoft Visio 2013 : Using the Organization Chart Wizard with new data
Technology FAQ
- Is possible to just to use a wireless router to extend wireless access to wireless access points?
- Ruby - Insert Struct to MySql
- how to find my Symantec pcAnywhere serial number
- About direct X / Open GL issue
- How to determine eclipse version?
- What SAN cert Exchange 2010 for UM, OA?
- How do I populate a SQL Express table from Excel file?
- code for express check out with Paypal.
- Problem with Templated User Control
- ShellExecute SW_HIDE
programming4us programming4us